California Concerns Over New $2.7B Reservoir


California state officials voiced mounting concern this week over long-standing delays and cost overruns in the proposed Pacheco Reservoir expansion, a multibillion-dollar project that has yet to secure critical permits or water rights, years after initial funding was promised, according to a report by The Mercury News.

Why It Matters

The Pacheco Reservoir Expansion Project, a joint effort by Valley Water, the San Benito County Water District, and the Pacheco Pass Water District, represents a long-term strategy to strengthen the reliability of safe, clean drinking water supplies amid the challenges of climate change.

But the project’s escalating costs—now estimated at $2.7 billion, nearly triple the original $969 million estimate—and its failure to secure much-needed permits attracted scrutiny, according to the report.

Newsweek reached out to the California Water Commission and Valley Water via email for comment.

Dam rendering
Project rendering of potential dam and expanded reservoir, northwest view toward the City of San José.

Valley Water

What To Know

Members of the California Water Commission, an agency appointed by Governor Gavin Newsom, expressed dissatisfaction Wednesday with a lack of progress and shifting timelines.

The commission had committed $504 million in state bond funding to the project seven years ago, but signaled that funding may be reconsidered if progress stalls further.

“This is more about tracking the progress and making sure these projects are all going forward rather than backward,” commissioner Jose Solorio said. “Maybe down the road we do have to look at ways of lowering investments if there’s not sufficient progress in terms of viability.”

Commissioner Sandra Matsumoto said, “As we move forward in time, the uncertainties should be decreasing.”

Matsumoto added: “But I feel like the more we hear from the public, the more additional issues are coming up that make it sound less likely.”

The proposal calls for a new 320-foot earthen dam on North Fork Pacheco Creek, about two miles north of Highway 152. According to Valley Water’s website, the expansion project would boost Pacheco Reservoir’s operational capacity from 5,500 acre-feet to up to 140,000 acre-feet, enough to supply up to 1.4 million residents with water for one year in an emergency.

It would also reduce the frequency and severity of water shortages during droughts, according to Valley Water.

However, The Mercury News reported that the commission was told on Wednesday that the project had yet to obtain the key permits required to begin construction, had not secured the necessary water rights, and had completed just 30 percent of the design.

District officials estimated that by next year, they would have spent $132 million and completed 60 percent of the design. Delays were attributed to legal challenges from environmental groups, newly discovered geological complications, and inflation.

What People Are Saying

Melanie Richardson, Santa Clara Valley Water District’s interim CEO, told the commission, per The Mercury News: “An expanded Pacheco Reservoir is an excellent option for our agency and our region…

“It would provide a critical source of emergency storage in the event of an earthquake, a levee failure, or any other catastrophe. Having Pacheco as part of our system would improve our agency’s operational flexibility allowing for more efficient management of our water resources.”

Shani Kleinhaus, an advocate with the Santa Clara Valley Bird Alliance, said, per The Mercury News: “Valley Water continues to spend millions of dollars on a project that will cost many, many billions and is not feasible, and encumbers taxpayers and ratepayers with unjustifiable tax and rate increases. Hopefully, you will find a way not to promote this.”

What Happens Next

Officials now estimate that construction will not begin before 2029 and will not be finished until at least 2036. The initial goal was for construction to be completed by 2032.



Source link

  • Related Posts

    Red Sox Make Trade, Acquire Slugging First Baseman/Outfielder From Angels

    By J.P. Hoornstra writes and edits Major League Baseball content. A veteran of 20 years of sports coverage for daily newspapers in California, J.P. covered MLB, the Los Angeles Dodgers,…

    Updated IPL 2025 Points Table After Lucknow Super Giants Beat Gujarat Titans

    Gujarat Titans messed up on a golden opportunity to seal a top two spot in the league table as Lucknow Super Giants earned a consolation 33-run victory riding…

    You Missed

    Red Sox Make Trade, Acquire Slugging First Baseman/Outfielder From Angels

    • By admin
    • May 22, 2025
    • 3 views
    Red Sox Make Trade, Acquire Slugging First Baseman/Outfielder From Angels

    Updated IPL 2025 Points Table After Lucknow Super Giants Beat Gujarat Titans

    • By admin
    • May 22, 2025
    • 3 views
    Updated IPL 2025 Points Table After Lucknow Super Giants Beat Gujarat Titans

    How to Buy Jacksonville Jaguars Chubbies Swim Trunks: Shop NFL Chubbies Collection

    • By admin
    • May 22, 2025
    • 2 views
    How to Buy Jacksonville Jaguars Chubbies Swim Trunks: Shop NFL Chubbies Collection

    Rishabh Pant Slams No-Look Six For LSG vs GT. Shot Goes Viral. Watch

    • By admin
    • May 22, 2025
    • 2 views
    Rishabh Pant Slams No-Look Six For LSG vs GT. Shot Goes Viral. Watch

    California Concerns Over New $2.7B Reservoir

    • By admin
    • May 22, 2025
    • 3 views
    California Concerns Over New $2.7B Reservoir

    India Test Squad For England Tour 2025, LIVE Updates: Team Selection “Was Deferred By Two Weeks Due To…” – Report’s Big Revelation

    • By admin
    • May 22, 2025
    • 2 views
    India Test Squad For England Tour 2025, LIVE Updates: Team Selection “Was Deferred By Two Weeks Due To…” – Report’s Big Revelation